Nippon Paper nears 20MW biomass cogen plant startup in Washington after two years of construction in $85 million project

Read so far

Nippon Paper nears 20MW biomass cogen plant startup in Washington after two years of construction in $85 million project

September 19, 2013 - 08:14
Posted in:

PORT ANGELES, WA, Sept. 6, 2013 (Peninsula Daily News) - After more than two years of construction and controversy,Nippon Paper Industries USA's expanded biomass cogeneration plant is stirring to life in preparation for going online in October.

"We're doing checkouts of various pieces of equipment," mill manager Harold Norlund said last week from his Ediz Hook office.

He sat in front of a picture window dominated by the cogeneration plant's conical biomass-fuel silo and related buildings.

Peninsula Daily News - Testing to begin before Nippon biomass facility goes online next month